top of page
Crown Cardinal Overlay.png

Crown Cardinal Subdivision

New Bremen, Ohio

THE PLAN

VTF Excavation was contracted to develop 29 residential lots, including full underground utilities and engineered grading. The plan emphasized coordinated sequencing of multiple utility systems and efficient site preparation to create development-ready lots while maintaining long-term reliability and stormwater management.

THE WORK

VTF Excavation completed approximately 60,000 CY of mass earthwork to establish site grades and drainage patterns across the 29-lot expansion, with excavation depths reaching 14 ft. Crews installed 4,500 LF of watermain, 6,000 LF of sanitary sewer with 17 structures, and 8,000 LF of storm pipe—including 4,000 LF of perforated drain tile—along with 36 storm structures. The existing retention pond was relocated while maintaining stormwater flow capacity and overall drainage performance.


Work was carefully sequenced to integrate multiple utility systems while maintaining proper elevations and structural integrity. Coordination with electric and gas providers ensured steady progress as the subdivision advanced toward completion.

THE RESULTS

VTF Excavation delivered 29 fully serviced, development-ready lots on schedule despite spring weather conditions. The project met all engineering standards and demonstrates VTF’s expertise in large-scale residential development through successful coordination of multiple utility systems and site preparation, supporting future homes and continued community growth.

Project Highlights
  • Sitework: Mass grading and approximately 60,000 CY of earthwork; excavation depths reaching 14 ft
    Residential Lots: Development of 29 fully serviced lots averaging ½ ac each

  • Storm Sewer: 8,000 LF of storm pipe, including 4,000 LF of perforated drain tile, with 36 structures
    Sanitary Sewer: 6,000 LF of sanitary sewer with 17 structures

  • Water Infrastructure: 4,500 LF of watermain installation

  • Curb & Gutter: 5,172 LF of Type 2 curb and gutter installed, including 490 SF of ADA curb ramps

  • Asphalt: 7,050 SY of new roadway constructed using 3,040 tons of asphalt, with 3,360 SF of roadway widening on the existing roadway

  • Stone: 2,800 tons of stone for asphalt road base installed within 1% tolerance of the planned quantity

START DATE: Mar 2025

SUBSTANTIAL COMPLETION: Aug 2025

RESTORATION COMPLETION: TBD 2026

DJI_0051.JPG
DJI_0874.JPG
DJI_0316.JPG

Project Facts

Owner(s)

Crown Equipment Corporation

Download Project Profiles

  • Facebook
  • Instagram

©2026 by VTF Excavation.

bottom of page