Timberridge Sanitary & Dustman Interceptor

Bluffton, Indiana

THE PLAN

The Timberridge Sanitary and Dustman Interceptor project was designed to upgrade and expand Bluffton’s sanitary sewer system, improving reliability and capacity while rehabilitating aging infrastructure. The plan included deep gravity sewer and force main installations, bedrock excavation, lift station upgrades, and directional drilling to minimize surface disruption.

THE WORK

VTF Excavation installed 19,750 LF of 8”–12” gravity sanitary sewer with depths over 28’ and 1,050 LF of sanitary laterals for the Timberridge system, including a 32’ deep lift station and 207 CY of bedrock excavation. Crews also installed 10,000 LF of 10” HDPE force main and 2,000 LF of 2” force main using directional drilling to minimize disruption. 


For the Dustman Interceptor, the team installed 10,100 LF of 8“–24” gravity sanitary sewer at depths over 25’ and completed two existing lift station rehabilitations, requiring precise sequencing, coordination, and strict safety protocols throughout deep excavations and directional drilling operations.

THE RESULTS

The project successfully expanded and modernized Bluffton’s sanitary sewer network, providing reliable service, increased capacity, and improved infrastructure longevity. This project was delivered on-time and on-budget, demonstrating VTF Excavation’s ability to execute large-scale, complex municipal sewer projects safely and efficiently.

Project Highlights
  • Contracted Value: $8.2 million
    Gravity Sewer & Lift Station: 19,750 LF of 8”–12” gravity sanitary sewer with structures, 1,050 LF of sanitary laterals, and construction of a 32’ deep lift station, including 207 CY of bedrock excavation

  • Force Main: Installation of 10,000 LF of 10“ HDPE force main and 2,000 LF of 2” force main using directional drilling methods.

  • Dustman Interceptor: 10,100 LF of 8”–24” gravity sewer with structures, two existing lift station rehabs

  • Complex Work: Deep sewer installations, directional drilling, bedrock excavation, and lift station construction

START DATE: July 2022

COMPLETION DATE: Nov 2023

map.jpg
Timberridge - Deep Sewer.JPG

Project Facts